Manufacturing / Power BI

    The parts were ready. The smaller jobs were still waiting.

    An illustrative manufacturing use case showing how Power BI can help separate material delays from production scheduling delays.

    Custom equipment manufacturing | Power BI + SQL Server + SharePoint

    This is a representative scenario. Project names, dates, and figures are synthetic and do not identify a client.

    The problem

    When orders shipped late, long-lead materials were often the first explanation. Some purchased parts did take months to arrive, so purchasing received much of the attention.

    But that didn’t explain every late order.

    Smaller jobs could have their drawings released and materials available, yet still wait for a production slot. Larger orders took priority, and those smaller jobs slipped.

    The solution

    Bring planned and actual milestone dates into one Power BI report, from order entry through shipment.

    For each job, the report shows when drawings were released, when materials were ready, when production started, and when the order shipped. Filter by project size to see whether smaller jobs follow a different pattern from larger orders.

    The key comparison is between being ready for production and actually starting. That helps the team distinguish a material problem from a scheduling problem and decide where to investigate.

    In this example, actual dates come from an ERP database on SQL Server. Planned dates and additional milestones come from SharePoint lists or a planning spreadsheet.

    Explore the example

    Use the filters to compare small, medium, and large projects. Start with Small and look at Materials Ready, Production Start, and Ship.

    Average milestone variance (days from plan)

    Order Entry
    0
    Drawings Released
    1
    Materials Ready
    4
    Production Start
    12
    Production Complete
    14
    Ship
    16

    Green = ahead of plan. Red = behind plan. The report shows where dates moved, not why a scheduling decision was made.

    ProjectOrder EntryDrawings ReleasedMaterials ReadyProduction StartProduction CompleteShip
    P00010-12182122
    P00021311578
    P0003-11-2234
    P0004024101213
    P000510-1242629
    P0006-11391112
    P00070-21345
    P000812157810
    P0009023212426
    P0010-10-3122
    P0011036121516
    P00121-1281011
    P0013014111315
    P0014-110161921
    P0015029101314
    P001610-27910
    P00170-21273032
    P0018-114356
    P0019124192224
    P002001-2232528
    P0021031881012
    P0022-10291213
    P00231-13202325
    P0024025131517

    What to notice

    In the example data, materials for most small jobs are ready close to plan. The more consistent delays appear at Production Start and continue through shipment.

    Larger jobs generally start closer to their planned dates.

    That pattern points to a scheduling gap worth reviewing. It does not prove why a job was deprioritized. A scheduling review would still need to confirm available capacity, job dependencies, promised dates, and the rules used to sequence work.

    The practical value is knowing where to ask the next question. The manufacturer can review how smaller jobs are prioritized and give customers delivery dates that better reflect the production schedule.

    Are ready jobs still waiting to get onto the schedule? Start with a Reverse Solution diagnostic.

    Start the Conversation